Views: 0 Author: Site Editor Publish Time: 2026-08-06 Origin: Site
Step-by-Step Leak Pressure Testing Procedure for RDHX Water Connections
1. Pre-Test Preparation (Before filling coolant)
Confirm all pipe fittings, quick-disconnect couplings, ball valves and gaskets are fully installed and tightened properly; replace any scratched or deformed O-rings.
Close the rack isolation valves to separate this RDHX loop from the main CDU manifold.
Disconnect IT power to the rack as a safety precaution during testing.
Prepare test tools: hand air pressure pump, pressure gauge, stopwatch, spray bottle with soapy water, absorbent wipes.
2. Dry Air Pressure Test (Primary test, no liquid inside)
This is the most reliable method to find hidden micro leaks without spilling coolant.
Connect the air pump to the RDHX supply test port; fully close the return valve to seal the closed loop.
Slowly pressurize the internal water circuit to 1.5 times the system working pressure (standard operating pressure 0.8–1.0 MPa → test pressure 1.2–1.5 MPa).
Lock the pressure valve and start timing for a 30-minute holding test.
Check the pressure gauge continuously:
Pressure drop ≤0.02 MPa in 30 mins: connections pass the air test.
Obvious pressure drop: spray soapy water on all joints, coil welds and ports. Bubbles will form at leak points for easy identification.
Mark leaking fittings, fully release pressure, re-seal or replace components, then repeat the air test until stable.
3. Coolant Filling & Flushing Test
Release all air pressure completely, then open the vent valves on the top of the RDHX manifold.
Slowly fill the secondary glycol coolant from the CDU until liquid flows steadily out of the air vents (no air bubbles). Close all vent valves.
Restore normal operating pressure (0.8–1.0 MPa) and keep the loop static for 2 hours.
Visually inspect every joint, drip tray, coil base for dripping, damp marks or liquid accumulation. Wipe all pipe connections dry first to spot tiny seepages easily.
4. Dynamic Running Test (Simulate real working conditions)
Start the CDU pump to circulate coolant at design flow rate.
Run the full circulation for 24 hours continuously:
Check connections every 4 hours for seepage or condensation.
Monitor temperature fluctuations; abnormal temperature differences may signal hidden partial blockages or slow leaks.
If no dampness, drips or pressure loss appears after 24h dynamic operation, the water connections are leak-free.
5. Post-Test Acceptance Standard
No visible liquid seepage at any fittings, coil body or weld seams.
Static air pressure holds steady with negligible drop.
Drip tray remains dry with zero liquid accumulation after full testing.
No new white mineral residue (sign of micro seepage) on pipe joints.
6. Troubleshooting Tips if Leaks Are Found
Minor seepage at quick couplings: Disconnect, replace the dual O-rings, re-lubricate with EPDM silicone grease and re-lock.
Threaded joint dripping: Loosen, re-wrap PTFE tape evenly, retighten to the specified torque (do not over-tighten).
Coil weld micro-leaks: Return the RDHX unit for factory re-brazing.
Condensation water droplets (not pipe leaks): Improve rack air sealing gaskets or adjust supply water temperature to avoid dew point crossing.